Standard Laying Conditions for Ductile Iron Pipe

Type 1*
Flat-bottom trench.** Loose backfill.
Type 2
Flat-bottom trench.** Backfill lightly consolidated to centerline of pipe.
Type 3
Pipe bedded in 4-inch minimum loose soil.*** Backfill lightly consolidated to top of pipe.
Type 4
Pipe bedded in sand, gravel, or crushed stone to depth of 1/8 pipe diameter, 4-inch minimum. Backfill compacted to top of pipe. (Approximately 80% Standard proctor, AASHTO T-99.)
Type 5
Pipe bedded to its centerline in compacted granular material, 4-inch minimum under pipe. Compacted granular or select material*** to top of pipe. (Approximately 90% Standard Proctor, AASHTO T-99.)


*For 14-inch and larger pipe, consideration should be given to the use of laying conditions other than Type 1.

**"Flat-bottom" is defined as "undisturbed earth."

***"Loose soil" or "select material" is defined as "native soil excavated from the trench, free of rocks, foreign material, and frozen earth."